West Seattle light rail extension pushed back
Sound Transit gave an updated timeline for starting service on the West Seattle Link Extension to 2035 following an agency timeline review.
SEATTLE - The light rail extension to West Seattle is being pushed back again.
Officials with Sound Transit announced on Thursday it’s estimated that it will open in 2035 following updated timeline calculations driven by cost-saving efforts and construction complexity over the Duwamish River.
Key factors impacting the light rail timeline
The backstory:
In late 2024, Sound Transit reported higher-than-expected cost estimates for the West Seattle project, prompting board leaders to order a sweeping cost-reduction plan. At the same time, the agency initiated an effort to address a projected $35 billion funding gap over the next quarter-century.
These efforts paused final design work and property purchases until an updated system plan was adopted in May, according to Sound Transit. '
Sound Transit Board votes to expand light rail to West Seattle, Tacoma, not Ballard
The Sound Transit Board has passed a motion for the future ST3 light rail expansion plan to add lines in West Seattle, Everett and Tacoma, but not Ballard.
Closer look at the project
What we know:
The West Seattle Link Extension will add 3.9 miles of service connecting SODO to Alaska Junction.
The agency's revised schedule sets the start of passenger service for 2035, adding roughly two to three years to the overall project delivery timeline, according to transit officials.
A comprehensive cost-savings effort identified more than $2 billion in reductions to lower overall project expenses after higher-than-expected costs were reported in late 2024.
Independent reviews confirmed that building a new light rail-only crossing over the Duwamish River requires more time during the construction phase, according to transit staff.
Sound Transit worked with the City of Seattle to move 230-kilovolt transmission lines within the rail route, avoiding construction along 6th Avenue S.
What's next:
Sound Transit anticipates the agency’s Board of Directors will work on appropriating funds and advancing construction planning.
Board members plan to authorize land acquisitions and set aside money for property purchases and planning, with major construction contracts expected to be awarded in 2027, according to Sound Transit.
The Source: Information in this story came from Sound Transit and original reporting by FOX 13 Seattle.
MORE NEWS FROM FOX 13 SEATTLE
3 arrested after shooting at Seattle police officers
Seattle Mayor Katie Wilson recall petition: What to know
Monroe man charged with murder, child assault after lengthy investigation
Here's where fires in Washington state are burning
Seattle detective slams city over 5-hour mass shooting briefing response
Hit-and-run driver leaves Seattle skateboarder in critical condition
To get the best local news, weather and sports in Seattle for free, sign up for the daily FOX Seattle Newsletter.
Download the free FOX LOCAL app for mobile in the Apple App Store or Google Play Store for live Seattle news, top stories, weather updates and more local and national news.